Laurel Finishing Kitchen Updates
The Multi-Purpose Building at Laurel Elementary School functions as a makeshift kitchen serving pre-packaged food. The scope of this project is to construct a fully equipped kitchen addition (1000 sf) that includes on-site preparation of hot meals, a self-serve salad/fruit bar and chilled milk. Scope in the Multi-Purpose Building includes seismic strengthening, re-roofing, acoustical improvements, fire alarm system upgrades & water bottle station.
MONTHLY CONSTRUCTION UPDATE
Nutritional Services moved into new kitchen on 5/24
ADA accessible parking stall striped & opened for use
Relocate outdoor tables to playground and new patio
Establish new outdoor lunch patio (see map above)
and more
WEEKLY CONSTRUCTION UPDATE
Passed Final Health Dept. Inspection on 5/7
Turned-over Kitchen keys to Nutritional Services on 5/8
Contractor demobilized from premises on 5/10
Paint stripes for accessible parking stall by 5/17
Activities in June/July 2019
Remove temp kitchen appliances in classroom #13
Deep clean classroom #13 & re-install classroom furniture
Construction activities in May 2019
Turnover Multi-Purpose Room to school on 5/3
Final Health Dept Inspection (May 7th)
Turnover Kitchen to Nutritional Services on 5/10
Paint stripes for accessible parking stall
Open entry gates facing Patterson Ave (May 6th See Map)
WEEKLY CONSTRUCTION UPDATE
MPR: wax flooring (April 29th)
Move back cafeteria tables (April 29th & 30th)
Fire Alarm testing (6pm to10pm Wed. May 1st)
Repave Accessible Parking Stall (4/30, 5/1 or 5/2)
Remove construction fence barriers (May 2nd, See Map)
Open entry gates facing Patterson Ave (May 2nd,See Map)
Final Health Dept Inspection (May 7th)
Complete Kitchen Staff Training (May 10th)
OPERATIONAL GOALS:
Multi-Purpose Room: student assembly on Fri. 5/3, Science night, Reading night, & 5th Grade Promotion.
WEEKLY CONSTRUCTION UPDATE
Final Fire Alarm testing (Tentative May 1st & Sat May 4th)
MPR: wax flooring (week of April 22nd)
ADA Accessible Parking Stall: Repave (week of April 22nd)
Final Health Dept Inspection (April 25th)
Complete Kitchen Staff Training (week of April 22nd)
Move back cafeteria tables (April 29th & 30th)
Remove construction fence barriers (4/30 tentative)
OPERATIONAL GOALS:
Multi-Purpose Room: hold Science night, Reading night, & 5th Grade Promotion.
Construction activities thru April & May 2019
More Fire Alarm testing school-wide (April and May)
MPR: Clean dust, wax flooring & dry clean curtains (April)
ADA Accessible Parking Stall: repave & pour new concrete curb required to level out (April)
Install new exterior gates; install exterior ladder (April)
Commissioning/Testing of Kitchen Appliances (April)
Health Dept Inspection (April)
Kitchen Staff Training (April & May)
Building & Grounds Mechl/Electl/Plumbing Training (May)
NOISE:
HORNS will sound off during final fire alarm test on Saturday morning 4/6
Construction activities thru April 2019
MPR Fire alarm system upgrades (100% completed)
MPR: Clean dust, wax flooring & dry clean curtains
ADA Accessible Parking Stall: repave & pour new concrete curb required to level out.
Install new exterior gates; install exterior ladder
Commissioning/Testing of Kitchen Appliances
Health Dept Inspection
NOISE:
Intermittent HORNS sounding off during fire alarm system testing on Friday 3/22 6:15pm to 8pm, Thurs. 3/28 3:30pm to 8pm & Saturday 4/6 9am to 1pm.
Construction activities
Fire alarm system upgrades in Multi-Purpose Bldg.
Fire alarm system testing in March (flyer will be distributed to neighborhood - see attached)
Test fire suppression eqpt
Paint exterior roof mounted eqpt
NOTICE: Fire Alarm testing, click to read more
Construction activities
Continue connecting water, power, gas & drains for oven, dishwasher, sinks, refrigerator, freezer & hoods.
Install fire suppression equipment
Paint exterior roof mounted equipment
Install network data cabling