Update for 2018-08-03

Heads–up: SATURDAY WORK scheduled on 8/4, 8/11, 8/18. Noise levels will be moderate. Starts at 8am to 3pm.

School starts on 8/13/18

  • Outdoor construction activities
  • Nail Roof Plywood Multi-Purpose Bldg (continues to 8/20)
  • Drilling inside Multi-Purpose Bldg (continues to 9/30) 
  • Install Shingle Roofing Multi-Purpose Bldg (8/21 — 9/30)
  • Misc. Saw Cutting
  • Concrete pour (to last approx. 3 hours) scheduled on Friday 8/10. 

Jim Carter III