Update for 2018-08-10

Heads–up: SATURDAY WORK scheduled on 8/11, 8/18, 8/25, 9/1, 9/8, 9/15, 9/22, 9/29. Noise levels will be low to moderate. Start 8am to 3pm.

School starts on 8/13/18

Outdoor construction activities

  • Pour Concrete Tuesday 8/21 (& tentatively Friday on 8/31)
  • Nail Roof Plywood Multi-Purpose Bldg (continues to 8/20)
  • Drill inside Multi-Purpose Bldg (continues to 9/30)
  • Install Shingle Roofing Multi-Purpose Bldg (8/21 — 9/30)
  • Saw Cutting (intermittent)
Jim Carter III