Outdoor construction activities

  • Pour Concrete Footings re-scheduled to Tuesday 8/28
  • Install underground Plumbing 8/29—9/7
  • Nail Roof Plywood (Multi-Purpose Bldg) continues to 9/1
  • Install Shingle Roofing (Multi-Purpose Bldg) 9/4 — 9/30

    Look ahead: Concrete pour for Kitchen Floor tentatively 9/11