Update for 2018-08-24

Heads–up: SATURDAY WORK scheduled on 8/25, 9/8, 9/15,
9/22, 9/29.

NO WORK on Fri. 8/31, Sat. 9/1 & Mon. 9/3 (Labor Day)

Outdoor construction activities

  • Pour Concrete re-scheduled from Tues 8/28 to Thurs 8/30
  • Nail Roof Insulation (Multi-Purpose Bldg) 8/25—8/30
  • Nail Shingle Roofing (Multi-Purpose Bldg) 9/4—9/14
  • Install kitchen floor rebar & plumbing 9/4—9/10

    Look ahead: Concrete pour for Kitchen Floor tentatively 9/11
Screen Shot 2018-08-26 at 4.01.24 PM.png
Jim Carter III