Update for 2018-09-07

Heads–up: SATURDAY WORK on 9/8, 9/15, 9/22, 9/29, 10/6, 10/13, 10/20 & 10/27

Highlights:

  • Patterson street encroachment removed

  • Re-roofing of Multi-Purpose Bldg completed

Outdoor construction activities

  • Concrete pour re-scheduled to Monday 9/10 11am—3pm

  • Install underground plumbing for new Kitchen 9/11—9/17

  • Install rebar for kitchen floor 9/18—9/25

Look ahead:

  • Concrete pour for Kitchen floor 9/26 (tentative date)

  • Drill Seismic anchors inside Multi-Purpose Bldg

Jim Carter III