Update for 2018-09-14

Heads–up: SATURDAY WORK on 9/22, 9/29, 10/6,10/13, 10/20 & 10/27

Highlights: No work planned Saturday 9/15

Outdoor construction activities

  • Install forms & rebar for remaining concrete footings

  • Install underground plumbing for new Kitchen

  • Install rebar for kitchen floor

Look ahead:

  • Concrete pour for remaining foundation (exact date TBA)

  • Concrete pour for Kitchen floor (exact date TBA)

  • Drill Seismic anchors inside Multi-Purpose Bldg (TBA)

Jim Carter III