Heads–up: SATURDAY WORK 9/29, 10/6,10/13, 10/20 & 10/27

Highlights: No work planned Saturday 9/22

Construction activities

  • Concrete pour for remaining kitchen footings 9/26 or 9/27

  • Install underground plumbing for Kitchen

  • Install rebar for kitchen floor

  • Anchor & Drill Steel Columns inside Multi-Purpose Bldg

(seismic strengthening) 9/19 to 10/5

Look ahead:

  • Concrete pour for kitchen floor (exact date TBA)