Highlights: underground plumbing completed

Construction activities

  • Install forms & rebar for kitchen floor 10/12 - 10/17

  • Pour Concrete for kitchen floor 10/18 or 10/19

  • Seismic Strengthening inside Multi-Purpose Bldg

(Drilling on-going thru 10/26)

Look ahead: Start framing kitchen walls & roof week of 10/22