Update for 2018-10-05

Construction activities

  • Install scaffolding inside MPR on Saturday 10/6

  • Install underground plumbing for Kitchen 10/1 - 10/11

  • Install rebar for kitchen floor 10/12 - 10/17

  • Anchor & Drill Steel Columns inside Multi-Purpose Bldg

(seismic strengthening) - on-going thru to 10/5

Look ahead: Concrete pour for kitchen floor (approx. 10/18)

Jim Carter III