Update for 2018-11-16

School & Office closed today. 
These 3 photos illustrate activities in progress continuing thru next week:

Kitchen: Exterior & Interior framing 
Multi-Purpose Bldg: started installing acoustical ceiling tiles 

image1.jpeg
image2.jpeg
image3.jpeg
Jim Carter III