Update for 2018-11-30
Highlights: Completed acoustical improvements (on 11/29) in
Multi-Purpose Bldg to reduce ambient noise.
Construction activities
Frame exterior kitchen roof & install plywood sheathing
Rough-in of interior electrical and plumbing
Look ahead:
Power & Gas Outtages school wide 12/26/18 thru 1/4/19
Sewer pipe trenching in Patterson St. during winter break 12/26/18 thru 1/4/19). Required to connect new kitchen.