Update for 2018-12-07

Heads–up: SATURDAY WORK on 12/8 & 12/15 to gain time.

Highlights: framing moving swiftly to beat rain

Construction activities

  • Continue roof framing & plywood sheathing

  • Rough-in of interior electrical, fire alarm, plumbing & mechl ducting

Image 2018-12-21 at 5.14.04 PM.png
Jim Carter III