Update for 2019-01-11

Highlights:

  • Sewer service pipe installed gas service pipe

  • installed, electrical service installed, new fire alarm panel

  • installed, interior sheetrocking completed & roofing installed.

Construction activities

  • Install fiber reinforced washable wall panels

  • Install suspended ceiling

  • Install roof mounted fans & vent pipes (delayed by rain)

  • Plaster exterior walls (delayed by rain)

Look ahead:

  • Install kitchen appliances

  • Install plants fronting Patterson Avenue

Jim Carter III