Update for 2019-01-25

Construction activities

  • Install epoxy flooring 1/23—1/29

  • Install exterior plaster 1/18—1/31

Look ahead:

  • Install kitchen appliances, sinks & hoods

Project Delay:

  • Divisions of State Architect has mandated additional fire alarm system upgrades in the Multi-Purpose Building

Image 2019-01-28 at 11.08.58 AM.png