Update for 2019-04-19

WEEKLY CONSTRUCTION UPDATE

  • Final Fire Alarm testing (Tentative May 1st & Sat May 4th)

  • MPR: wax flooring (week of April 22nd)

  • ADA Accessible Parking Stall: Repave (week of April 22nd)

  • Final Health Dept Inspection (April 25th)

  • Complete Kitchen Staff Training (week of April 22nd)

  • Move back cafeteria tables (April 29th & 30th)

  • Remove construction fence barriers (4/30 tentative)

OPERATIONAL GOALS:

  • Multi-Purpose Room: hold Science night, Reading night, & 5th Grade Promotion.

Jim Carter III