Update for 2019-04-19
WEEKLY CONSTRUCTION UPDATE
Final Fire Alarm testing (Tentative May 1st & Sat May 4th)
MPR: wax flooring (week of April 22nd)
ADA Accessible Parking Stall: Repave (week of April 22nd)
Final Health Dept Inspection (April 25th)
Complete Kitchen Staff Training (week of April 22nd)
Move back cafeteria tables (April 29th & 30th)
Remove construction fence barriers (4/30 tentative)
OPERATIONAL GOALS:
Multi-Purpose Room: hold Science night, Reading night, & 5th Grade Promotion.