Update for 2018-10-26
Heads–up: SATURDAY WORK on 10/27 includes painting inside the multi-purpose room.
Highlights: Seismic Strengthening of Multi-Purpose Bldg Completed
Concrete Poured for Kitchen Floor
Construction activities
Build exterior kitchen walls 10/24 - 11/9
Install sheetrock inside Multi-Purpose Bldg
Look ahead: Start framing kitchen roof 11/9