Update for 2019-06

MONTHLY CONSTRUCTION UPDATE

  • Nutritional Services moved into new kitchen on 5/24

  • ADA accessible parking stall striped & opened for use

  • Relocate outdoor tables to playground and new patio

  • Establish new outdoor lunch patio (see map above)

  • and more

Read More
Jim Carter III
Update for 2019-05-10

WEEKLY CONSTRUCTION UPDATE

  • Passed Final Health Dept. Inspection on 5/7

  • Turned-over Kitchen keys to Nutritional Services on 5/8

  • Contractor demobilized from premises on 5/10

  • Paint stripes for accessible parking stall by 5/17

Activities in June/July 2019

  • Remove temp kitchen appliances in classroom #13

  • Deep clean classroom #13 & re-install classroom furniture

Read More
Jim Carter III
Update for 2019-05-03

Construction activities in May 2019

  • Turnover Multi-Purpose Room to school on 5/3

  • Final Health Dept Inspection (May 7th)

  • Turnover Kitchen to Nutritional Services on 5/10

  • Paint stripes for accessible parking stall

  • Open entry gates facing Patterson Ave (May 6th See Map)

Read More
Jim Carter III
Update for 2019-04-26

WEEKLY CONSTRUCTION UPDATE

  • MPR: wax flooring (April 29th)

  • Move back cafeteria tables (April 29th & 30th)

  • Fire Alarm testing (6pm to10pm Wed. May 1st)

  • Repave Accessible Parking Stall (4/30, 5/1 or 5/2)

  • Remove construction fence barriers (May 2nd, See Map)

  • Open entry gates facing Patterson Ave (May 2nd,See Map)

  • Final Health Dept Inspection (May 7th)

  • Complete Kitchen Staff Training (May 10th)

OPERATIONAL GOALS:

  • Multi-Purpose Room: student assembly on Fri. 5/3, Science night, Reading night, & 5th Grade Promotion.

Read More
Jim Carter III
Update for 2019-04-19

WEEKLY CONSTRUCTION UPDATE

  • Final Fire Alarm testing (Tentative May 1st & Sat May 4th)

  • MPR: wax flooring (week of April 22nd)

  • ADA Accessible Parking Stall: Repave (week of April 22nd)

  • Final Health Dept Inspection (April 25th)

  • Complete Kitchen Staff Training (week of April 22nd)

  • Move back cafeteria tables (April 29th & 30th)

  • Remove construction fence barriers (4/30 tentative)

OPERATIONAL GOALS:

  • Multi-Purpose Room: hold Science night, Reading night, & 5th Grade Promotion.

Read More
Jim Carter III
Update for 2019-04-05

Construction activities thru April & May 2019

  • More Fire Alarm testing school-wide (April and May)

  • MPR: Clean dust, wax flooring & dry clean curtains (April)

  • ADA Accessible Parking Stall: repave & pour new concrete curb required to level out (April)

  • Install new exterior gates; install exterior ladder (April)

  • Commissioning/Testing of Kitchen Appliances (April)

  • Health Dept Inspection (April)

  • Kitchen Staff Training (April & May)

  • Building & Grounds Mechl/Electl/Plumbing Training (May)

Read More
Jim Carter III
Update for 2019-03-29

NOISE:

HORNS will sound off during final fire alarm test on Saturday morning 4/6

Construction activities thru April 2019

  • MPR Fire alarm system upgrades (100% completed)

  • MPR: Clean dust, wax flooring & dry clean curtains

  • ADA Accessible Parking Stall: repave & pour new concrete curb required to level out.

  • Install new exterior gates; install exterior ladder

  • Commissioning/Testing of Kitchen Appliances

  • Health Dept Inspection

Read More
Jim Carter III
Update for 2019-03-08

Construction activities

  • Fire alarm system upgrades in Multi-Purpose Bldg.

  • Fire alarm system testing in March (flyer will be distributed to neighborhood - see attached)

  • Test fire suppression eqpt

  • Paint exterior roof mounted eqpt

NOTICE: Fire Alarm testing, click to read more

Read More
Jim Carter III
Update for 2019-02-22

Construction activities

  • Continue connecting water, power, gas & drains for oven, dishwasher, sinks, refrigerator, freezer & hoods.

  • Install fire suppression equipment

  • Paint exterior roof mounted equipment

  • Install network data cabling

Read More
Jim Carter III
Update for 2019-02-15

Construction activities

  • Finish connecting water, power, gas & drains for oven, dishwasher, sinks, refrigerator, freezer & hoods.

  • Install fire suppression equipment

  • Misc. exterior concrete patch work

  • Install interior doors

Read More
Jim Carter III
Update for 2019-02-08

Construction activities

  • Finish connecting water, power, gas & drains for oven, dishwasher, sinks, refrigerator, freezer & hoods.

  • Install fire alarm smoke detectors, strobes and horns.

Read More
Jim Carter III
Update for 2019-01-25

Construction activities

  • Install epoxy flooring 1/23—1/29

  • Install exterior plaster 1/18—1/31

Project Delay:

  • Divisions of State Architect has mandated additional fire alarm system upgrades in the Multi-Purpose Building

Read More
Jim Carter III
Update for 2019-01-11

Highlights:

  • Sewer service pipe installed gas service pipe

  • installed, electrical service installed, new fire alarm panel

  • installed, interior sheetrocking completed & roofing installed.

Read More
Jim Carter III
Update for 2018-12-21

ALERTS:

fire alarm horns will sound-off (school-wide) for 15 minutes

required to test the system on 12/26 or 12/27 (around 9am)

Construction activities

  • Power & Gas Outages school wide 12/26/18 thru 1/4/19

  • Start sewer pipe work on 12/26 (see details attached)

  • Continue with electrical, fire alarm, plumbing & mechl

  • Start sheetrocking interior walls on 12/27

  • Start exterior plaster wall finish on 12/27

Read More
Jim Carter III
Update for 2018-12-14

Heads–up: WORK SATURDAY12/15 & 12/22 (rain permitting).

Highlights: framing moving swiftly to beat rain

Construction activities

  • Continue roof framing & plywood sheathing

  • Continue rough-in electrical, fire alarm, plumbing & mechl

  • Install roofing

  • Install exterior lath & plaster base coats

Read More
Jim Carter III
Update for 2018-12-07

Highlights: framing moving swiftly to beat rain

Construction activities

  • Continue roof framing & plywood sheathing

  • Rough-in of interior electrical, fire alarm, plumbing & mechl ducting

Read More
Jim Carter III
Update for 2018-11-30

Highlights: Completed acoustical improvements (on 11/29) in

Multi-Purpose Bldg to reduce ambient noise.

Construction activities

  • Frame exterior kitchen roof & install plywood sheathing

  • Rough-in of interior electrical and plumbing

Read More
Jim Carter III
Update for 2018-11-16

School & Office closed today. 
These 3 photos illustrate activities in progress continuing thru next week:

Kitchen: Exterior & Interior framing 
Multi-Purpose Bldg: started installing acoustical ceiling tiles 

Read More
Jim Carter III