Construction activities
Finish connecting water, power, gas & drains for oven, dishwasher, sinks, refrigerator, freezer & hoods.
Install fire suppression equipment
Misc. exterior concrete patch work
Install interior doors
Project Delays:
Revision to oven hood adding delay days
Divisions of State Architect has mandated additional fire alarm system upgrades in the Multi-Purpose Building