Update for 2019-02-22

Construction activities

  • Continue connecting water, power, gas & drains for oven, dishwasher, sinks, refrigerator, freezer & hoods.

  • Install fire suppression equipment

  • Paint exterior roof mounted equipment

  • Install network data cabling

Project Delays:

  • oven hood change submitted to health dept. for approval.

  • fire alarm upgrades in the Multi-Purpose Building submitted to

  • Division of the State Architect for approval.

Jim Carter III