Update for 2019-02-22
Construction activities
Continue connecting water, power, gas & drains for oven, dishwasher, sinks, refrigerator, freezer & hoods.
Install fire suppression equipment
Paint exterior roof mounted equipment
Install network data cabling
Project Delays:
oven hood change submitted to health dept. for approval.
fire alarm upgrades in the Multi-Purpose Building submitted to
Division of the State Architect for approval.