NOISE:

HORNS will sound off during final fire alarm test on Saturday morning 4/6

Construction activities thru April 2019

  • MPR Fire alarm system upgrades (100% completed)

  • MPR: Clean dust, wax flooring & dry clean curtains

  • ADA Accessible Parking Stall: repave & pour new concrete curb required to level out.

  • Install new exterior gates; install exterior ladder

  • Commissioning/Testing of Kitchen Appliances

  • Health Dept Inspection

OPERATIONAL GOALS:

  • Multi-Purpose Room: hold Science night, Reading night, & 5th Grade Promotion.

Kitchen opens for service in August 2019