Update for 2019-03-29
NOISE:
HORNS will sound off during final fire alarm test on Saturday morning 4/6
Construction activities thru April 2019
MPR Fire alarm system upgrades (100% completed)
MPR: Clean dust, wax flooring & dry clean curtains
ADA Accessible Parking Stall: repave & pour new concrete curb required to level out.
Install new exterior gates; install exterior ladder
Commissioning/Testing of Kitchen Appliances
Health Dept Inspection
OPERATIONAL GOALS:
Multi-Purpose Room: hold Science night, Reading night, & 5th Grade Promotion.
Kitchen opens for service in August 2019