Update for 2019-04-05

Construction activities thru April & May 2019

  • More Fire Alarm testing school-wide (April and May)

  • MPR: Clean dust, wax flooring & dry clean curtains (April)

  • ADA Accessible Parking Stall: repave & pour new concrete curb required to level out (April)

  • Install new exterior gates; install exterior ladder (April)

  • Commissioning/Testing of Kitchen Appliances (April)

  • Health Dept Inspection (April)

  • Kitchen Staff Training (April & May)

  • Building & Grounds Mechl/Electl/Plumbing Training (May)

OPERATIONAL GOALS:

  • Multi-Purpose Room: hold Science night, Reading night, & 5th Grade Promotion.

  • Kitchen opens for service in August 2019

Jim Carter III