Update for 2019-04-05
Construction activities thru April & May 2019
More Fire Alarm testing school-wide (April and May)
MPR: Clean dust, wax flooring & dry clean curtains (April)
ADA Accessible Parking Stall: repave & pour new concrete curb required to level out (April)
Install new exterior gates; install exterior ladder (April)
Commissioning/Testing of Kitchen Appliances (April)
Health Dept Inspection (April)
Kitchen Staff Training (April & May)
Building & Grounds Mechl/Electl/Plumbing Training (May)
OPERATIONAL GOALS:
Multi-Purpose Room: hold Science night, Reading night, & 5th Grade Promotion.
Kitchen opens for service in August 2019