Update for 2019-06
MONTHLY CONSTRUCTION UPDATE
Nutritional Services moved into new kitchen on 5/24
ADA accessible parking stall striped & opened for use
Relocate outdoor tables to playground and new patio
Establish new outdoor lunch patio (see map above)
Deliver classroom #13 furniture on 6/5
Move old kitchen appliances to warehouse on 6/5
Deep clean classroom #13
Re-stripe parking lot stalls w/ fresh coat of paint
Relocated outdoor tables to upper yard
Install fence barrier between new patio & parking lot on 6/18
Install plants facing Patterson St. (Building & Grounds)
Conduct final fire alarm testing on 6/19 3:30pm to 7:30pm