Update for 2018-10-26

Heads–up: SATURDAY WORK on 10/27 includes painting inside the multi-purpose room.

Highlights: Seismic Strengthening of Multi-Purpose Bldg Completed

Concrete Poured for Kitchen Floor

Construction activities

  • Build exterior kitchen walls 10/24 - 11/9

  • Install sheetrock inside Multi-Purpose Bldg

Look ahead: Start framing kitchen roof 11/9

Read More
Jim Carter III
Update for 2018-10-12

Highlights: underground plumbing completed

Construction activities

  • Install forms & rebar for kitchen floor 10/12 - 10/17

  • Pour Concrete for kitchen floor 10/18 or 10/19

  • Seismic Strengthening inside Multi-Purpose Bldg

Read More
Jim Carter III
Update for 2018-10-05

Construction activities

  • Install scaffolding inside MPR on Saturday 10/6

  • Install underground plumbing for Kitchen 10/1 - 10/11

  • Install rebar for kitchen floor 10/12 - 10/17

  • Anchor & Drill Steel Columns inside Multi-Purpose Bldg

(seismic strengthening) - on-going thru to 10/5

Look ahead: Concrete pour for kitchen floor (approx. 10/18)

Read More
Jim Carter III
Update for 2018-09-28

Construction activities

  • Install underground plumbing for Kitchen 10/1 - 10/11

  • Install rebar for kitchen floor 10/12 - 10/17

  • Anchor & Drill Steel Columns inside Multi-Purpose Bldg

Read More
Jim Carter III
Update for 2018-09-21

Construction activities

  • Concrete pour for remaining kitchen footings 9/26 or 9/27

  • Install underground plumbing for Kitchen

  • Install rebar for kitchen floor

  • Anchor & Drill Steel Columns inside Multi-Purpose Bldg

Read More
Jim Carter III